Relocation Of Sealant Filling Unit To Hannover (II)
Demolition work completed
The demolition work was completed as planned, if not because of the good preparation by our contractor »Elektro Heese«. Many old cables had to be removed previously to the demolition – and many more had to be temporarily re-routed.
Fortunately, there were no unpleasant surprises during the demolition work. The soil tests were positive. Because we now have building permission, nothing is in the way of constructing the new building, Thus we can start everything as planned.
Another part of the factory building was gutted to later serve as additional storage space. Here, up way into the 90s, the laboratories of »Weserland Bautenschutz GmbH« were situated. Up to now some load-bearing walls are still in the way. After the static of the roof structure is reinforced, these walls can be removed, too.